BLADE PRO MOTOR GRADER CONTROL SYSTEM INSTALLATION. - Continued
BLADE PRO MOTOR GRADER CONTROL SYSTEM INSTALLATION. - Continued

Laser Leveling Equipment (Lle) For Graders, Dozers, & Scrapers Page Navigation
  130    131    132    133    134  135  136    137    138    139    140  
img
TM 5-6675-348-13&P
(71) Install two Cylinder Lines (39) and two Float Valve Lines (35) to T-fittings (40).
(72) Tighten two Cylinder Lines (39) and Float Valve Lines (35) to T-fittings (40).
(73) Tighten 90-degree fittings (41) and T-fittings (40).
(74) Install gaskets (56) on Hydraulic Valve
Cables marked RAISE (57) and
LOWER (58).
Hydraulic Valve Cables are marked
RAISE and LOWER. Failure to install
Hydraulic Valve Cables in the correct
positions may cause damage to
equipment.
NOTE
Remove protective caps from
Proportional Valve Assembly electrical
terminals before installing Hydraulic
Valve Cables.
(75) Install Hydraulic Valve Cable (RAISE) (57) on Proportional Valve Assembly Terminal (59).
(76) Secure Hydraulic Valve Cable (RAISE) (57) to Proportional Valve Assembly Terminal (59) with
screw (60).
(77) Tighten screw (60).
(78) Install Hydraulic Valve Cable (LOWER) (58) on Proportional Valve Assembly Terminal (61).
(79) Secure Hydraulic Valve Cable (LOWER) (58) to Proportional Valve Assembly Terminal (61) with
screw (62).
(80) Tighten screw (62).
(81) Route Hydraulic Valve Cables (57) and (58) behind Proportional Valve Assembly (51).
(82) Cable tie Hydraulic Valve Cables (57) and (58) together as needed.