TM 5-6675-348-13&P
(148) Install R/L Switch (109) on left-side
RAISE/LOWER Lever (105).
(149) Tighten jam nuts (106) and (99).
NOTE
Install cable ties as required.
The Power Cables for all switches
are routed the same. The Remote
Switch on the Articulation Lever is
shown.
Steps (150) through (153) apply to
both sides.
(150) Route Remote Switch Cable (110)
from Remote Switch (108), down
Articulation Lever (103), and across to
column (95).
(151) Remove screw (111) from column (95).
(152) Install Remote Switch Cable (110), R/L
Switch Cable (112), Loop Clamp (113),
and screw (111) on steering column (95).
(153) Cut Remote Switch Cable (110) and
R/L Switch Cable (112) to 26 in. (66 cm),
as measured from Loop Clamp (113).