Adjust mast swivel mount (2) until
mast (3) is plumb.
(4)
Set OFF/ON/SET-UP switch (4) to ON
position.
(5)
Position left side of blade (1) over known
elevation point.
(6)
Enter desired cross-slope, using Increase/
Decrease switch (5) on right side of
Operator Interface Box (6). Ensure slope
direction is correct direction of Slope
switch (7).
(7)
Place R/L switch (8) on right side in
automatic position. Automatic
Indicator (9) should be green.
(8)
Adjust Increase/Decrease switch (5) on
left side of Operator Interface Box (6)
until center green bar (10) is illuminated,
indicating on grade.
(9)
Position OFF/ON/SET-UP switch (4) to
SET-UP position.
NOTE
REFERENCE will be displayed on
Operator Interface Box.
(10) Use Increase/Decrease switch (5) on right
side of Operator Interface Box (6) to enter
actual elevation of bottom edge of blade.
(11) Place OFF/ON/SET-UP switch (4) back to
ON position.
NOTE
Both LEDs should be green.
(12) Place R/L switch (8) on left side to
automatic position, and cycle the switch
through MANUAL and back to AUTO.
(13) Begin grading (TM 5-3805-261-10).
3-48