(12) Remove two bolts (12).
(13) Install Power Cable (11), two Loop
Clamps (8), and existing bolts (12).
(14) Tighten bolts (12).
(15) Strip approximately 12 in. (30.5 cm) of
insulation from end of Power
Cable (11).
(16) Route Power Cable (11) into left side of
Battery Box (13).
Allow solder to cool before handling
wire. Failure to comply may result in
injury to personnel.
(17) Solder two connections (14) to Red
Wire (15) and Black Wire (16).