TM 10-4510-206-14
Section IV.
ORGANIZATIONAL MAINTENANCE PROCEDURES
4-9.
GENERAL
CAUTION
Whenever performing any maintenance procedure involving
the disconnection/reconnection of electrical wiring, be
sure to perform the procedure in paragraph 2-7.1 before
placing the Bath Unit back into service. Failure to do
so could result in damage to either or both of the water
pump and the fuel and blower motors.
This section provides instructions for inspection, service, replacement or
repair of assemblies and subassemblies of the Bath Unit.
Each maintenance
procedure contains step-by-step instructions for the task to be performed.
Where necessary, a final test will be performed on the serviced or repaired
item to assure minimum performance.
4-10
MISCELLANEOUS ITEMS MAINTENANCE PROCEDURES
a.
Power Cable Assemblies.
These instructions tell how to test the power
cables by checking continuity.
1.
Check continuity of Bath Unit cable from one male connector pin
(1) to mating pin on female connector (2). Repeat procedure for
remaining four connector pins.
2.
Repeat step 1 by checking continuity from each male connector pin
to mating pins on remaining female connector.
4-18
Change 4