TM 10-4510-206-14
5-7.
REPAIR PROCEDURES (CONT'D)
1.
Welded Boiler Tank and Skid (Cont'd)
28.
Install
29.
Install
30.
Install
31.
Install
32.
Install
33.
Install
master control box assembly (paragraph 5-6.m).
low water probe assembly (paragraph 5-6.1).
UV scanner (paragraph 5-6.i).
blower assembly (paragraph 4-14.i).
ignition cables (paragraph 4-14.h).
instructional, identification, and warning plates
(paragraph 4-14.g).
34.
Install manifold connections and fittings (paragraph 4-14.f).
35.
Install temperature high limit and operating control (paragraph
5-6.k).
36.
Install conduit, electrical fittings and wiring (paragraph
4-14.d).
37.
Install ignition transformer (paragraph 4-14.c).
38.
Install burner head assembly (paragraph 4-14.g).
39.
Install fuel supply control assembly (paragraph 4-14.a).
40.
Install smokestack assembly (paragraph 4-10.d).
5-56